Repository navigation
Release Review: ModelAsAService r2.2 (rc Sync26) - #86
Conversation
CAMARA Validation — PASS0 errors, 0 warnings, 31 hints | Profile: standard |
|
@camaraproject/release-management_reviewers Thank you for your review and for documenting the findings in #74. We have completed the necessary updates to address these issues, and the snapshot has been restarted to reflect the latest changes. Please let us know if everything looks good on your end. Thanks again for your efforts and guidance! |
There was a problem hiding this comment.
Hi team,
you went a bit too quick as I had not completed the review :-)
Please see 2 additional sub issues in #78.
I have now completed the review, but you will need to do a new snapshot.
tanjadegroot
left a comment
There was a problem hiding this comment.
Hi team, many thanks for the quick update, it looks good !
As the 2 additional review findings concern only test cases (most of which are enhanced cases), you may decide to address these now or later.
I can approve the release-candidate as it stands.
/LGTM
|
Hi @tanjadegroot, Thank you for the review and for your flexibility! We really appreciate your approval. Those are indeed great suggestions regarding the test cases. We will definitely address them as soon as possible. We will go ahead and merge this PR now. Thanks again for all your help and guidance throughout this review : ) |
|
This release-candidate is ready for merge ! Then please prepare the public release where the main work is
|
Release Review: r2.2 rc
This PR finalizes the reviewable release content for the active snapshot.
Edit and review this PR before merging it into the release snapshot. After Codeowner and Release Management approval, merging this PR creates the draft release.
Release contents
0.2.0-rc.20.2.0-rc.10.2.0-rc.20.2.0-rc.10.2.0-rc.20.2.0-rc.1Dependencies: Commonalities r4.4, ICM r4.2
Codeowner Actions
Tick each box once done. Ticking the last box — "The release is ready for Release Management review" — starts the Release Management review.
Update the CHANGELOG
What to do:
Document deferred validation warnings (and hints)
What to do:
The release is ready for Release Management review
Check that:
Tick this box to confirm readiness and to start the Release Management review.
Release Management Actions
The following actions and checks are done by a Release Management reviewer before approving the PR:
mainPR are collected as sub-issues of one issue titledRelease r2.2 review findings(see Recording review findings)Required release assets per API status
public
public
M = Mandatory, O = Optional — Full documentation
Valid next actions for codeowners
/discard-snapshot <reason>in the Release Issue to discard this snapshot, return toplanned, and update content onmainSnapshot:
r2.2-f2a7cdf