cpp-critical-path-validator

license: MIT python: 3.10+ tests version: 0.1.0 AACE: 49R--06

Critical path validation, logic health assessment, and optimization recommendations for Primavera P6 schedules — plus a full DCMA 14-Point Assessment.

Maintained by Critical Path Partners — a forensic-scheduling consultancy.

Companion to cpp-cpm-engine and cpp-xer-parser.


Scope and status

This is v0.1.0, and it is a public subset. Critical Path Partners maintains a larger internal validator; what this repository publishes is the nine-check core, the DCMA 14-Point assessment, the driving-path tracer and the HTML dashboard. It does not carry every check or output the internal version has.

Nothing here is a stub. The code in scripts/ is the code that runs, the tests in tests/ are the tests that guard it, and CI runs them on three operating systems across Python 3.10 to 3.12. What this repository is not is a mirror of the internal tool, so a report produced by Critical Path Partners should not be assumed to have come from this file set.

scripts/xer_parser.py is vendored byte for byte from cpp-xer-parser at commit 5fc6c5e, so the validator stands alone with no install step. CI verifies the vendored copy against that pinned commit on every push, and separately reports, without failing the build, when upstream has moved past it.


What it does

This validator answers the question every scheduler and every claims expert eventually asks: is this critical path actually correct, or is it artificial?

It runs nine independent checks on a Primavera P6 schedule:

# Check What it catches
1 Critical path identification Are CP activities reasonable in count and % of incomplete work?
2 Constraint-driven criticality Hard constraints overriding network logic — the #1 source of false CP.
3 Open ends Missing predecessor / successor on incomplete activities.
4 Relationship quality FF / SS on CP without an FS backbone (fragile CP).
5 Lag analysis Negative lags (leads) on CP that mask true duration.
6 Out-of-sequence progress In-progress activities ahead of their predecessors.
7 Near-critical fragility Activities with TF 1–10 days that could become the new CP with minor slip.
8 Logic continuity Activities that contribute work but have no logic path to project finish.
9 Constraint saturation Schedule-wide hard-constraint density vs DCMA 5% threshold.

Plus a CP Confidence Score (0–100, weighted across all 9 checks), an HTML dashboard, a DCMA 14-Point Assessment with all 14 checks, and a driving-path tracer.


Why this validator

The critical path is the single most consequential output of any schedule. Bid pricing depends on it. EOT entitlement turns on it. Forensic claims live or die on it.

And yet — in the field — far too many critical paths are artificial: forced by hard constraints, broken by open ends, made fragile by negative lags, or unconnected to the project finish milestone. A scheduler who relies on the CP without first auditing whether the CP is real is making a load-bearing decision on unverified ground.

The checks in this validator come out of court-filed forensic schedule analysis, so the audit is rigorous. Every finding is structured, cited (DCMA-EA PAM 200.1, AACE 49R-06), and includes the full list of affected activities, never truncated.


Install

git clone https://github.com/danafitkowski/cpp-critical-path-validator
cd cpp-critical-path-validator
# No external runtime dependencies. Just put scripts/ on your sys.path.

Pure Python 3.10+. The repo bundles its own copy of xer_parser.py plus minimal validation.py / config_profiles.py stubs, so it stands alone without separately installing companion repos.


Quick start

import sys
sys.path.insert(0, 'scripts')

from xer_parser import parse_xer
from cp_validator import validate_critical_path, generate_dashboard

# Parse the schedule
data = parse_xer('path/to/your.xer')

# Run all 9 checks
results = validate_critical_path(data)

# Generate the HTML dashboard
generate_dashboard(results, 'cp_validation_report.html')

# Or interrogate the results dict directly
print(f"CP Confidence Score: {results['cp_confidence_score']}/100")
print(f"CP Confidence Band:  {results['cp_confidence_band']}")

for check_name, check_data in results['checks'].items():
    print(f"  {check_name}: {check_data['rating']} — {check_data['note']}")

DCMA 14-Point Assessment

A separate, well-defined check suite with established federal-contract heritage.

from xer_parser import parse_xer
from dcma14 import dcma_14_assess

data = parse_xer('current.xer')
baseline = parse_xer('baseline.xer')  # optional; required for BEI

report = dcma_14_assess(
    data,
    baseline_data=baseline,
    profile='commercial',   # or 'nuclear' or 'mining'
)

print(f"DCMA Score: {report['dcma_score']}/14")
print(f"CPLI: {report['cpli']}")
print(f"BEI:  {report['bei']}")

for check_id, check in report['per_check'].items():
    print(f"  {check_id}: {check['severity']} — {check['message']}")

Three profiles bundle out of the box:

Profile Use case
commercial Generic commercial-construction defaults
nuclear Tightened thresholds for nuclear / heavy energy
mining Relaxed thresholds for resource-driven mining work

Clone and mutate the dict to add your own:

from config_profiles import get_profile

custom = get_profile('commercial')
custom['name'] = 'My Custom Profile'
custom['dcma_high_float_max_days'] = 30
report = dcma_14_assess(data, profile=custom)  # accepts dict or string

Driving path tracer

from dcma14 import trace_driving_path

# Walk the driving-predecessor chain for a CP activity back to project start
chain = trace_driving_path(data, task_code='A1050.20')
for step in chain:
    print(f"  {step['task_code']}  TF={step['total_float_days']}  drives via {step['rel_type']}")

Constraint taxonomy

Critical-path-validator distinguishes four tiers of constraint behavior:

Tier Codes Behavior
HARD_ABSOLUTE CS_MANDSTART, CS_MANDFIN P6 enforces the date regardless of network logic.
HARD_DATE CS_MSO, CS_MEO Pins the activity to a specific date; predecessor slips don't move it.
SOFT CS_MSOA, CS_MSOB, CS_MEOA, CS_MEOB Bounds the activity in one direction; logic drives the other edge.
PREFERENCE CS_ALAP Changes scheduling preference (late-date scheduling); no date bound.

Recommendations are tier-specific so schedulers know whether they are removing a Mandatory (overrides logic) or a Start-On (pins a date).


CP Confidence Score

Weighted average across all 9 checks (weights sum to 1.00):

Check Weight
Critical path identification 5%
Constraint-driven criticality on CP 17%
Open ends on CP 20%
Relationship quality on CP 13%
Lag issues on CP 15%
Logic continuity 10%
Near-critical fragility 10%
Out-of-sequence 5%
Constraint saturation (schedule-wide) 5%

Score bands:

Score Band Meaning
80–100 High confidence CP is logic-driven and reliable.
60–79 Moderate confidence CP has issues but is directionally correct.
40–59 Low confidence CP needs significant corrections.
0–39 Unreliable CP is artificial; do not rely on it for planning.

AACE alignment

The validator cites:

Reference What it covers
AACE Recommended Practice 49R-06 Identifying the Critical Path (LPM / TFM / MFP)
DCMA 14-Point Assessment The 14 schedule-quality metrics (DCMA-EA PAM 200.1)
NDIA PASEG Baseline Execution Index

Earlier revisions of this table also listed AACE 24R-03 and AACE 67R-11 with descriptions that were wrong: 24R-03 is "Developing Activity Logic", has no numbered sections, and is not a criticality standard; 67R-11 is "Contract Risk Allocation", not a forensic-competency document. Nothing in this repo cites either, so both rows were removed. The DCMA row previously misattributed the 14 metrics to federal acquisition regulations; their actual home is DCMA-EA PAM 200.1.


Running the tests

python tests/test_cp_validator.py     # validator core
python tests/test_dcma14.py           # DCMA 14-Point
python tests/test_cp_forensic.py      # forensic-correctness regressions

Or with pytest:

pip install pytest
pytest tests/

All tests build their XER fixtures synthetically in memory; no real client XER files ship with the repo.


Integration with the CPP forensic suite

CP validation is the first thing Critical Path Partners runs on a new XER, checking whether the CP is real before any forensic delay analysis, time impact analysis, or claims-package work begins. That job is done by the internal validator described under Scope and status; this repository publishes its nine-check core so anyone can run the same audit.

When cpp-cpm-engine is on the same sys.path, the validator's Check 2 also runs an LPM-confirmed-false-CP detection that cross-validates the schedule's reported critical path against an independently-computed LPM result.

When the engine is not available, the validator gracefully degrades (Check 2 still runs the constraint-driven analysis; the LPM cross-check is skipped).


License

MIT — see LICENSE.

You may use this validator in commercial forensic consulting, in academic research, in your own scheduling product, in court-filed expert reports. Just keep the copyright notice.


Contributing

See CONTRIBUTING.md. Bug reports and pull requests are welcome.


Companion repositories


Strategic note

Critical Path Partners is a forensic-scheduling consultancy. We open-source the foundational tooling because every academic, every solo forensic, every contractor's internal scheduler now has a reason to install CPP and a citation pathway. The math is a commodity; the workflow and discipline are not.

If you ship something built on this validator, we'd like to hear about it: criticalpathpartners.ca.

About

Critical Path Partners - critical path validation, DCMA 14-Point assessment, and logic health review for Primavera P6 schedules

Topics

Resources

Contributing

Security policy

Stars

0 stars

Watchers

0 watching

Forks

Releases

Packages

Contributors

Languages